🏭 Water & Sewer Impact

Data center water consumption, discharge, and municipal infrastructure impact

Overview

Data centers are among the most water-intensive industrial facilities, using millions of gallons daily for cooling systems. At full expansion, the IronGate facilities on Bielenberg Drive could dramatically increase Woodbury's water consumption during a period of documented drought stress.

Critical Context (Aug 17, 2026): Woodbury's watershed entered Minnesota DNR Drought Warning Phase on August 17, 2026 — the same month the interim ordinance was approved. Summer water use was already at 71% of firm capacity, with restrictions triggered at 93% and a full ban at 96%.

Water Consumption: IronGate's Usage

What We Know:

  • 401 Bielenberg: Marketed as "closed-loop" cooling system (less water than open towers, but still significant)
  • 500 Bielenberg: Discharge to sanitary sewer (10 MW operational + 24 MW planned)
  • Actual consumption figures: NOT PUBLICLY DISCLOSED

What We Don't Know:

  • Gallons per day (GPD) for each facility
  • Seasonal variation in water demand
  • Impact on municipal water supply at full build-out (100 MW)
  • Cooling tower discharge composition and contaminants
Data Gap: John Sebastian's August 2026 fact sheet estimated ~80,000 homes' worth of electricity at 100 MW build-out, but water consumption remains unquantified by the developer.

Woodbury's Water Supply Context

Metric Current Status (Aug 2026) Risk Level
Drinking water source 20 groundwater wells; zero surface water 100% dependent on groundwater
Drought status Drought Warning Phase (Aug 17, 2026) 2 steps from full emergency
Summer water use 71% of firm capacity Approaching critical threshold
Restriction triggers 93% = restrictions; 96% = full ban Only 22–25% capacity cushion
PFAS treatment plant Temporary blending system (2026) Permanent plant not online until 2028
Timing concern: Full data center build-out is planned before permanent PFAS treatment is in place. Any discharge contamination adds burden to temporary system.

Key Questions for Interim Ordinance Study

Water Consumption:

  • What is the actual water consumption (GPD) at 401 and 500 Bielenberg?
  • How does this compare to Woodbury's residential and commercial baseline?
  • What percentage of firm water capacity would full build-out (100 MW) consume?

Discharge & Contamination:

  • What biocides and corrosion inhibitors are used in cooling towers?
  • Where does discharge go (sanitary sewer, stormwater, on-site treatment)?
  • Has water quality testing been done post-expansion?

Drought & Supply:

  • Will water restrictions apply equally to data centers and residents?
  • What is the coordination with St. Croix River watershed management during droughts?
  • Can Woodbury's groundwater sustain both residential demand AND data center expansion during drought years?

Related Investigation Areas

Stormwater & Sewer Capacity: 500 Bielenberg discharges cooling water to sanitary sewer. At full build-out, this could strain municipal treatment capacity. Met Council SAC (Stormwater Abatement Charge) determinations should be reviewed.

Groundwater Depletion: Twenty wells support a city of ~70,000 residents. Data center water draw during drought cycles could trigger restrictions on residential use.

PFAS Contamination: Temporary blending system is in place until 2028. Cooling tower discharge could complicate PFAS management during this transition.